  | 
                | 
             
            
              | Photo of the Canyon Lake Dam in 1964 
                before reservoir impoundment begun. Photo Courtesy of US Army Corps 
                of Engineers | 
                | 
             
           
            
              
                |   | 
                  | 
               
              
                  | 
                Canyon Lake running over the spillway 
                  in July 2002. Photo Courtesy of the Comal County Engineer's Office | 
               
              
                |   | 
                 | 
               
              
                |   | 
                  | 
               
              
                |   | 
                The spillway waters destroyed part 
                  of the South Access Road in July 2002. Photo Courtesy of the Comal 
                  County Engineer's Office | 
               
              
                |   | 
                 | 
               
              
                |   | 
                  | 
               
              
                |   | 
                The spillway waters destroyed part 
                  of the South Access Road in July 2002. Photo Courtesy of the Comal 
                  County Engineer's Office | 
               
              
                |   | 
                 | 
               
              
                |   | 
                  | 
               
              
                |   | 
                The spillway waters 
                  carved a scenic new gorge out of the limestone bedrock in July 2002. | 
               
             
            The site initially identified for Canyon Dam was about five miles upstream 
      from New Braunfels. After the 308 report, additional hydrologic studies 
      were done, and the underlying limestone rock was found to be so honey-combed 
      and porous that engineers had serious concerns about major leakage that 
      could occur. Large losses might make power generation infeasible, so Chief 
      Engineer E. A. Markham recommended additional study and did not recommend 
      the project at that time. The Board of Engineers for Rivers and Harbors 
      rejected the 308 Report recommendations for constructing Canyon Dam.
            
              
            There were major floods in 1936 and 1938, and a group of civic, business, 
              and agricultural leaders formed the Guadalupe-Blanco Basin Improvement 
              Association and started to demand the federal government take action on 
              flood control. The group asked Congress to authorize the Corps of Engineers 
              to reevaluate the Canyon Lake project, and the Corps issued a favorable 
              report that led to Congressional authorization for construction of the 
              Dam in the Rivers and Harbors Act of 1945. The Corps was instructed to 
              prepare a pre-construction report, the Definitive Project Report, which 
              it completed in 1951. The Report recommended moving the dam site about 
              16 miles upstream, and it also recommended postponing power generation 
              because leakage losses were still projected to account for as much as 
              25% of total storage. The engineers thought it would be better to wait 
              and see how much water would actually be available for power generation 
              so they could size the generating capacity accordingly. Final approval 
              for construction was given in the Flood Control Act of 1954.  
              
            
              
                  | 
                  | 
               
              
                Photo of the 
                  Canyon Lake Dam  | 
               
             
            In a letter to the Corps of Engineers in July 1955, the Texas Board of Water 
              Engineers reaffirmed the Guadalupe-Blanco River Authority's role as the 
              state agency with whom the Corps of Engineers should negotiate and coordinate 
              the details of construction and operation of Canyon Reservoir. In September 
              1957 the two agencies formalized their relationship as partners in the project 
              with a contract that allocated costs and operations & maintenance responsibilities.  
            
              
            After some funding delays were overcome, construction of Canyon Dam on 
              the Guadalupe River Mile 303 began in 1958. Water impoundment began in 
              1964 and essentially completed by June 1964; the conservation pool level 
              was reached in 1968. Canyon Dam was finally dedicated on April 20 1966. 
              The total cost was $20.2 million.  
              
            It was constructed to serve two purposes - flood control and water conservation. 
              Flood protection is provided to 157,250 acres of land downstream from the 
              dam. The high canyons of the upper Guadalupe have a channel capacity of 
              40,000-50,000 cubic feet per second. The channel on the lower Guadalupe 
              River has a capacity of only 13,000-30,000 cubic feet per second; therefore, 
              the lower Guadalupe River Basin had been especially subject to serious flooding. 
              The construction of Canyon Dam on the edge of the Balcones Escarpment has 
              been very effective in protecting the lower Guadalupe River Basin.  
            
             
              
                  | 
                  | 
               
              
                Photo of the Canyon 
                  Lake Dam. Photo Courtesy of US Army Corps of Engineers  | 
               
             
            At conservation pool level the lake has a capacity of 382,000 acre-feet. 
      It has a surface area of 8,230 acres and 80 miles of shoreline. At flood 
      control pool level of 943-ft msl, the lake has an additional capacity of 
      346,000 acre-feet making total storage 728,400 acre-feet.
            
              
            The Guadalupe-Blanco River Authority (GBRA) is the local agency with 
              rights to the water in the conservation pool of the lake. The Authority 
              contributed to the construction costs and currently pays the U.S. Government 
              annually for the portion of operation and maintenance costs attributed 
              to the conservation pool water. The water is used to operate several small 
              hydroelectric plants downstream from New Braunfels. It is also used by 
              the GBRA for municipal water supply, irrigation, and industrial uses. 
              GBRA began construction of a hydroelectric facility at Canyon Dam in August 
              1987; it was first put into service in February 1989. 
              
            To date, it has been estimated that millions of dollars in flood damage 
              has been averted from several major flood events in the area. In the ensuing 
              decades, with Canyon Dam in place, recreation and tourism flourished in 
              areas downstream that had previously been subjected to severe floods. 
              Homes, summer cottages, campgrounds, water outfitters, and tubing operations 
              all became commonplace and part of the south Texas culture.  
              
            The first major flood event occurred in August 1978 when the lake elevation 
              reached 930.6-ft msl. Within two days' time, 40 inches of rain fell on 
              the upper Guadalupe River. The river flowed into the lake at 115,000 cubic 
              feet per second causing the lake to rise 21.6 feet above the conservation 
              pool level of 909.0 feet above mean sea level. It was estimated that 24 
              million dollars of downstream damage was averted due to the flood protection 
              of Canyon Dam. 
              
            The flood in July 1987 reached a  maximum lake level   of 942.67-ft msl. In 1991-1992 floods, maximum elevation reached 937.77-ft   msl.  
            Another flood event occurred in late June to early August 1997 when the 
              maximum elevation was 937.6-ft msl. Canyon Dam controls floods originating 
              on the 1,432 square miles of drainage above the dam.  
              
            In July of 2002, a stubborn low-pressure system parked itself over the 
              region and much of south Texas received almost a year's worth of rainfall 
              in less than a week. Canyon Reservoir filled to capacity and water rushed 
              over the spillway for the first time ever. The southern access road to 
              the Dam was washed out, and more than 800 homes were destroyed or damaged. 
              With the reservoir at record levels, thousands of oak trees dotting the 
              shoreline began to suffer from a lack of oxygen and most were not expected 
              to survive. Discharges from the Dam had to be halted temporarily because 
              of rocks and debris that accumulated around the outlet structure. Residents 
              feared that when releases were initiated again, about 40 homes below the 
              dam would be flooded because rocks and debris that washed down the spillway 
              channel created a "plug" obstructing the Guadalupe's flow about 
              a mile below the Dam. The raging spillway waters created a scenic new 
              gorge, which the Guadalupe-Blanco River Authority leased from the Corps 
              of Engineers in October of 2005 to operate the site as a tourist attraction. 
              Click here for more information on the Canyon Lake 
                Gorge 
              
            The Dam has not been able to provide complete protection from floods. 
              In 1972, and again in 1998, intense rains below the Dam site resulted 
              in devastating floods in New Braunfels and areas downstream.  
              
            LAKE LEVELS: 
              
            909.0 ft msl - conservation pool 
             
              943.0 ft msl - spillway crest 
             
              948.0 ft msl - spillway crest, plus 5 feet spillway flow-high elevation 
              of flowage easement lands 
             
              899.7 ft msl - all time lowest lake pool after impoundment on December 
              13, 1984 
             
              950.32 ft msl - all time highest lake pool after impoundment on July 6, 
              2002.              |